UPDATE to Broadway Road Closure, Windlesham
Published: 27 August 2020
The drainage works on Broadway Road, Windlesham have had to
be extended. The reason for this is due to several issues that arose when
on site that have meant a redesign and lead to delays in the works.
The current road closure will be lifted at the end of day on Monday 1 September
The remaining works will need to be carried out under two way lights. The lights will remain in place for 24 hours a day during the works.
New dates and traffic management - Tuesday 1 September to Friday 4 September two-way lights 24 hours a day.
We expect the works to now be completed by Friday 4 September, depending on weather and no unforeseen problems that lead to delays.
Published 13th July 2020
Drainage works – 27 July, for 5
weeks, 24hr a day road closure
Roadworks during the coronavirus restrictions
The government and Department for Transport have asked the Highway Sector Council to make every effort to deliver essential highways projects on all local authority highway networks, whilst abiding by the COVID-19 safe working practices. We are therefore carrying out these works in line with central government and COVID-19 safe working practises and in accordance with the CLC Site Operating Procedures, endorsed by Public Health England.
The sub-contractor will have appropriate procedures in place to ensure their staff can comply with government advice. Please respect these workers as they deliver these highways services.
All key routes will remain open and safe for key workers. For more information visit www.ourroads.today.
If anything changes with the details of these works, we will let you know. You can also find up to date details of the works on www.surreycc.gov.uk/roadworks. If you have any questions please do not hesitate to contact us on works.communication@surreycc.gov.uk.
For more information please see below: